Beaver Dam Ana(B)log

we believe in learning from nature to preserve and restore natural systems.

Our goal in this project is to install imitation beaver dams (Beaver Dam Analogs or BDAs) along Mill Creek in the Emma Wetlands property of the Preserve. By doing this we can create diverse habitat and help mitigate urban flooding caused by the extensive amount of impervious surfaces in the City.

View our Beavers and Blue Heron page to get more context or learn about beavers. 

 
 

Inspiration for this project comes from the Beaver Restoration Guidebook.


2018 Ana(B)log Posts


June:

June 9th - A work day was hosted to prep posts for installation. Eleven people showed up to help and we managed to sharpen about 40 locust posts that will be driven into the creek bed. Since locust is extremely dense wood, it ended up being much more difficult to cut than originally expected and the two chainsaws that were brought dulled quite quickly. Even still, we managed to make good progress on the posts (100 more to sharpen), and we were even able to stage about one BDA's worth of posts at the site of installation. Originally we planned to cut the posts in a square wedge cut, but because of the difficulty a two-cut wedge would suffice.

 

June 7th - An organization called Growing Hearts has partnered with us for this project by providing 7 high school students to assist in this work with the mission to grow their resumes for college. For their first work day out of 5, the young adults gathered weeding materials (mostly Chinese Privet pulled on site), as well as calculated how many posts will be needed per BDA and how much river stone will be needed for the BDAs.

Per the Beaver Restoration Guidebook, the posts should be between 0.5 and 1 meter apart. Since we have 140 locust posts and each BDA site is about 25 feet wide. We figured we could finish 7 BDAs (about half of the total 13) during this round of installation.

The river stone will be used as support for the upstream side of the BDAs. We will use an aggregate of different stone sizes ranging from 2'' in diameter to 8''.  To determine how much stone we'll need, we calculated the cubic feet of a rectangular prism that sits like a ramp on the upstream side of the BDA. In the end, we calculated that we'll need 25 cubic feet of stone per BDA. Multiplied by 7 BDAs that gets us 125 cubic feet total. It's difficult to calculate the number of tons we'll need based on the volume because it's hard to tell how well the aggregate will compact, but we estimated 10 tons of river rock to get the 125 cubic feet. Below is a sketch of our brainstorming session with the participants from Growing Hearts:

 
Doc Jun 08, 2018, 12_24-1.jpg
 

May:

May 15th - Met with the Director of Public Spaces at Ed Castro Landscape, who will be providing equipment and people power to install the locust posts by the end of June. 

May 15th - Met with Lisa Casanova, a professor of microbiology at GSU. Along with her graduate students, Lisa will be collecting water quality data every week at every BDA site to establish specific baseline data.


April:

April 28th - Creek Cross-section Survey Complete. Thirteen BDA sites have been formally identified with stakes and four key creek locations were chosen to perform cross-section surveys. Water sampling at each BDA site weekly began.

 
 

April 10th - Delivery of 60 locust posts to be used as the main support for the BDAs. These are sourced by a supplier in Mountain City, GA and are all about 8 feet long and 6 - 8 inches in diameter.


March:

March 23rd - Met with key partners for this Beaver Dam Analog project, including local professors and a representative from an environmental engineering firm. From measuring the length of the creek (among other factors), we figured that the creek would benefit from 14 BDAs to raise the water table and connect the old creek bed.

March 12th - Met with Glen to discuss next steps. Decided to plan a site visit with key partners to discuss prep work, research opportunities, timeframe, etc. 


January:

January 9th - Initial meeting with Glen Bedhard with the City of Atlanta Department of Watershed to discuss the idea of installing Beaver Dam Analogs along Mill Creek, a tributary of Nancy Creek that flows through a significant portion of the Preserve.

Glen is familiar with the Beaver Restoration Guidebook and is supportive of this project and wants to help develop a plan specifically applicable to the strengths and opportunities at the Blue Heron Nature Preserve.


2015 BDA Attempt

It was our first attempt to apply this technique at the Preserve. Beavers had been active on Mill Creek for about 1 year and had built several dams on the current Mill Creek channel.  Unfortunately the heavy water flows during rain events which are indicative of urban streams blew them out.  The intention of the BDA installation was to take and existing beaver dam and reinforce it.   The BDA was located downstream from the beaver den which was separated from the main stream channel by a small channel.  The hope was to strengthen the dam and back up the water flow such that water would flow into the narrow channel and recharge the otherwise disconnected den to the Mill Creek

 

It was an all volunteer effort involving our partners from CH2M Hill and Georgia Gwinnett College.  We learned a lot including it is exceedingly difficult to drive posts into the creek bed using sledge hammers.  The BDA held up initially, but ultimately was blown out and abandoned by both the beavers and us.  Since then we continue to promote the idea and look for opportunities to fund this effort.